Friday, September 16, 2011

Pole Mapping and Survey DONE

 September 15, 2011, we divided our groups. The first group did the pole mapping and the other groups completed the survey, it is too hot but we need to accomplish our target. We went home with our tasks done.
Group 1 (Vj, Ariston and Aldwin)



Group 2 (BM, Jaq, and Elmar)

Friday, September 2, 2011

Elmar's Assignment

At the end of october, 2011, we receive a letter from PELCO 1 referring us to NEECO located in San Leonardo Nueva, Ecija.
September 1, 2011, we proceeded to NEECO 1. unfortunatey, they have no pole map of Pampanga.
September 2, 2011, we conducted a research on our equipments i.e. amplifiers, coaxial cable, compensation scheme, functions and qualifications of personnel, and organization law.